Back     2. Mobile Equipment

1.0 Crane Controls

Are These Controls in Place?

1.1 CRANE LIFT PLAN

Crane lift plan complete and signed off (includes certificates, training, loads, etc.)

1.2 PERMITS

All permits signed by all necessary personnel

1.3 CRANE INSPECTION

Crane inspection documents are complete and all issues addressed

1.4 CRANE OPERATOR

Crane operator is certified

1.5 SIGNAL PERSON

Signal person is qualified

1.6 RIGGERS

Riggers are qualified

1.7 CRANE SET-UP

Crane is safely set-up: good ground conditions, outriggers fully extended, etc.

1.8 CRANE SWING

Crane swing radius around counterbalance is danger taped or barricaded

1.9 CRANE RADIUS

Crane radius maintains safe distance from power lines (min. 20')

1.10 RIGGING

Rigging is in good working condition and marked with monthly safety color

1.11 FALL ZONE

Fall zones identified, and demarcated or have signal persons in place

1.12 SIGNAL PERSON (2)

Signal persons and/or riggers are in clear view of operator

1.13 UNDER LOAD

No worker is directly under the load

1.14 TAG LINES

Tag lines are used